Project Location: Suffield Block
Project Constraints:
• Model of existing facility was out of date
• 2 days maximum down time
Project Highlights:
• Created 3D rendering of the affected area
• Completed flare system piping studies
• Conducted multi-discipline design review
• Provided piping ISO and Bill of Material for the project
• Provided civil / structural drawings
• Fixed bid the mechanical construction
• Shop fabricated 100% of project piping
• Completed 98% of site construction while facility is live
• Reduced project install cost by 8-10%
• 1 day for final bolt up
• No re-work or field modifications